Answer:
$85,225
Step-by-step explanation:
The computation of the applied overhead is shown below:
Let us assume that the Direct labor be X
And, the factory overhead be 1.4X
As we know that
Cost of goods manufactured = Beginning work in process + direct material + direct labor + factory overhead - ending work in process
$213,300 = $35,100 + $57,200 + X + 1.4X - $25,100
$213,300 = $67,200 + 2.4X
$146,100 = 2.4X
X = $60,875
And, the factory overhead is
= $60,875 × 1.4
= $85,225
hence, the applied overhead is $85,225