Answer:
Direct labor cost= $31,200
Step-by-step explanation:
Giving the following information:
Production= 48,000 units
Standard time= 3 minutes per unit
Rate= $13 per hour
First, we need to calculate the number of hours required:
The proportion of minuted per hour= 3/60= 0.05
Number of hours= 48,000*0.05= 2,400 hours
Now, the direct labor cost:
Direct labor cost= 2,400*13= $31,200