Answer: $600F
Step-by-step explanation:
Given the following :
standard unit price - $1.80
actual purchase price per unit - $1.65
actual quantity purchased - 4,000
units actual quantity used - 3,900
units standard quantity allowed for actual production - 3,800 units
Material purchase price variance = ( Actual unit price of material - standard unit price of material) × Actual unit of material purchased
($1.65 - $1.80) × 4000
( $0.15) × 4000
$600F (Favorable) because standard price is higher than actual price