107k views
2 votes
Eighteen men take 15 days

to dig 6 hectares of land
Find the number of men
required to dig 8 hectares
in 12 days?


User Sherelyn
by
5.3k points

2 Answers

6 votes

Final answer:

The number of men required to dig 8 hectares in 12 days, when 18 men can dig 6 hectares in 15 days, is calculated by setting up a proportion of work done. The solution to the proportion gives us the answer of 16.875 men, which means 17 men are needed when rounding to a whole person.

Step-by-step explanation:

The question asks us to determine the number of men required to dig 8 hectares of land in 12 days, given that 18 men can dig 6 hectares in 15 days. This is a problem of direct proportion where we can use the concept of work to solve it. The work done by a certain number of workers in a given time is constant, and we set up a proportion based on the data provided.

The formula for work done (W) is W = number of men (M) × number of days (D) × area of land (A). From the question, we have for the first scenario, W1 = 18 men × 15 days × 6 hectares. For the second scenario, we are to find the number of men required (M2), so W2 = M2 × 12 days × 8 hectares.

Since the work done in both scenarios is equal (W1 = W2), we have 18 × 15 × 6 = M2 × 12 × 8. Simplifying this equation will give us the value of M2, which is the number of men needed. M2 can be calculated as follows:

M2 × 12 × 8 = 18 × 15 × 6
M2 = (18 × 15 × 6) / (12 × 8)
M2 = (18 × 15 × 6) / 96
M2 = 16.875

Since we cannot have a fraction of a man, we would need 17 men to dig 8 hectares in 12 days.

User MoreON
by
6.0k points
0 votes

Answer:

number of men = 30

Step-by-step explanation:

18 men takes 15 days to dig 6 hectares of land.

18 men will take 12 days to dig ? hectares of land

cross multiply

hectares of land = 12 × 6/15

hectares of land = 72/15

hectares of land = 4.8 hectares

18 men will take 12 days to dig 4.8 hectares of land

? number of men will take 12 days to dig 8 hectares

cross multiply

number of men = 18 × 8/4.8

number of men = 144/4.8

number of men = 30

User Fredrik Hedblad
by
5.6k points