Answer:
a. Job 301 = $19,500
Job 302 = $27,000
Job 303 = $52,500
b. Overhead applied for the year = $250,200
Under-applied overhead = $148,800
Explanation:
a. The computation of overhead was assigned to each of the three jobs, 301, 302, and 303 is shown below:-
Overhead application rate = Budgeted Overhead ÷ Application Base
Application base = Budgeted Overhead ÷ Budgeted Direct Labor costs
= $318,000 ÷ $1,060,000
= 0.3
Overhead assignment to jobs = Budgeted rate × Labor Cost
Job 301
= 0.3 × $65,000
= $19,500
Job 302
= 0.3 × $90,000
= $27,000
Job 303
= 0.3 × $175,000
= $52,500
b. The computation of over- or underapplied manufacturing overhead for year 1 is shown below:-
Overhead applied for the year = Total direct labor cost × Overhead rate
= $834,000 × 0.3
= $250,200
Under-applied overhead = Actual overhead - Applied overhead
= $399,000 - $250,200
= $148,800