Final answer:
Using the percentage of completion method, Red Builders should have recognized a profit of $300,000 at the end of year 1 for the construction project for Blue Co.
Step-by-step explanation:
To calculate the profit recognized by Red Builders at the end of year 1 for the construction project with Blue Co., we should use the percentage of completion method since revenue recognition over time is applied. This method recognizes revenue and profit based on the progress towards completion of the contract. The formula to calculate the profit recognized is:
Profit = (Cost incurred to date / Total estimated costs) × Total contract price - Cost incurred to date
Let's calculate it:
Total estimated costs at the end of year 1 are the cumulative costs incurred plus the estimated additional costs to complete, which is $1,200,000 + $3,600,000 = $4,800,000.
Calculate the percentage of completion, which is $1,200,000 (cost incurred to date) divided by $4,800,000 (total estimated costs), giving 25%.
Apply this percentage to the total contract price to get the revenue recognized, which is 25% of $6,000,000 = $1,500,000.
Profit recognized at the end of year 1 is therefore $1,500,000 (revenue recognized) - $1,200,000 (cost incurred to date) = $300,000.
The answer is (a) $300,000.