Answer:
The most the company would be willing to spend today on the project is
$1,253,529
Step-by-step explanation:
In order to calculate What is the most the company would be willing to spend today on the project we woule require to calculate first the cost of capital as follows:
cost of capital=(1-1/1.45)*4.83%*(1-35%)+(1/1.45)*10.87%
cost of capital=0.01498*0.65+0.0749=0.084637=8.4637%
Therefore, Maximum amount to be spent=$275,000/8.4637%*(1-1/(1+8.4637%)^6)=$1,504,124.98
Maximum amount to be spent=$1,253,529
The most the company would be willing to spend today on the project is
$1,253,529