D) if there is no other pattern in the samples, the process is in control.
Step-by-step explanation:
What happens is that, when preliminary samples are used for the construction of graphs, it is common to relate the control limits obtained to the tentative control limits.
Therefore, when the sample measurements fall within the control limits and there is no systematic behavior, it is concluded that the process is under control and that the tentative limits are appropriate.