Answer:
Total Cost of Job 50 = $28,800
Total Cost of Job 51 = $28,800
Cost per unit Job 50 = $144
Cost per unit Job 51 = $57.6
Explanation:
a. The computation of balance on the job cost sheets for Jobs 50 and 51 at the end of April is shown below:-
Particulars Job 50 Job 51
Number of units 200 500
Direct material
Job 50 (600 × $20) $12,000
Job 51 (1,300 × $16) $20,800
Direct labor
Job 50 (600 × $20) $12,000
Job 51 (400 × $12) $4,800
Overhead
Job 50 (600 × $8.00) $4,800
Job 51 (400 × $8.00) $3,200
Total cost $28,800 $28,800
Total Cost of Job 50 = Direct material + Direct labor + Overhead
= $12,000 + $12,000 + $4,800
= $28,800
Total Cost of Job 51 = Direct material + Direct labor + Overhead
= $20,800 + $4,800 + $3,200
= $28,800
b. The computation of cost per units at the end for Jobs 50 and 51 at the end of April is shown below:-
Cost per unit of Job 50 = Total cost of Job 50 ÷ Number of units of Job 50
= $28,800 ÷ 200
= $144
Cost per unit of Job 50 = Total cost of Job 50 ÷ Number of units of Job 50
= $28,800 ÷ 500
= $57.6