Answer:
0.89 orders per minute
Explanation:
As per the data given in the question,
Batch size = 4 orders
Here, process 1 = cooking
process 2 = Bagging and payment accepting
Time taken to complete process 1 by cooking a batch of 4 orders
= 3 × 1 + 0.5 × 3
= 4.5 minutes
Time taken to complete process 2 by Bagging and payment accepting of 4 orders
= 0.80 × 4
= 3.2 minutes
Time in process 1 is greater than time taken in process 2
Since, process 1 is bottleneck operation So, it will decide the capacity of project. therefore,
Overall capacity = 4.5 minutes for 4 orders
Therefore number of orders = 4 ÷ 4.5
= 0.89 orders per minute
Hence, Process capacity = 0.89 orders per minute