Which is the closet to the volume of the concrete needed to fill the pillar?

Which is the closet to the volume of the concrete needed to fill the pillar?-example-1
User Nynohu
by
8.4k points

1 Answer

6 votes

Answer:

c) 21.4

Explanation:

9.5 times 1.5 times 1.5 is 21.375 or 21.4 rounded