Answer:
For the present approach the value added time is 20 minutes, the non value added time is = 905 minutes, The total lead time = 925 minutes, the value added ratio is = 2.2%
For the proposed approach the value added time = 20 minutes, the non vale added time = 50 minutes, the total lead time = 70 minutes, the value added ratio is = 28.6 %
Step-by-step explanation:
Solution
The Present approach is:
Value added time (Process times, step 1 + Process times, Step 2 +Process times, Step 3, + Process times, Step 4)
= 5+8+4+3 = 20 minutes.
The non value added time = Total within batch wait time + move time
= [Total time required for the four steps * ( batch size -1)] + move time
= [(5+8+4+3)* (45-1)]+ 25
= 905 minutes
Now,
The total time lead = value added time + value non added time
= 20 +905 =925 minutes
so,
Value added ratio = value added time/total time
= 20 minutes/925 minutes = 2.2%
Proposed approach
Value added time (Process times, step 1 + Process times, Step 2 +Process times, Step 3, + Process times, Step 4)
= 5+8+4+3 = 20 minutes.
The non value added time = Total within batch wait time + move time
= [Total time required for the four steps * ( batch size -1)] + move time
= [(5+8+4+3)* (3-1)]+ 10
= 50 minutes
Thus,
The total time lead = value added time + value non added time
= 20 +50=70 minutes
The value added ratio = value added time/total time
= 20 minutes/70 minutes = 28.6%
Note: kindly find an attached copy o the complete question to of this solution below