44.4k views
1 vote
n January the company produced 3,380 units using 13,520 pounds of the direct material and 2,824 direct labor-hours. During the month, the company purchased 14,280 pounds of the direct material at a cost of $35,100. The actual direct labor cost was $75,841 and the actual variable overhead cost was $33,828. The company applies variable overhead on the basis of direct labor-hours. The direct materials purchases variance is computed when the materials are purchased. The labor rate variance for January is: Multiple Choice $407 F $407 U $2,833 U $2,833 F

User Lobsterism
by
7.6k points

1 Answer

5 votes

Answer:

Direct labor rate variance= (Standard Rate - Actual Rate)*Actual Quantity

Step-by-step explanation:

Giving the following information:

Actual direct labor hours= 2,824

Actual direct labor cost= $75,841

Actual direct labor rate= 75,841/2,824= $26.86

To calculate the direct labor rate variance, we need the standard cost information. I will provide the formula and an invented standard cost per hour to guide an answer.

Direct labor rate variance= (Standard Rate - Actual Rate)*Actual Quantity

Standard cost per direct labor hour= 30

Direct labor time (efficiency) variance= (30 - 26.86)*2,824

Direct labor time (efficiency) variance= $8,867.36 favorable

It is favorable because the cost per hour was lower than estimated.

User Alex Lyalka
by
8.1k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.