64.7k views
5 votes
Summary data for Benedict Construction Co.'s (BCC) Job 1227, which was completed in 2017, are presented below:

Bid Price: $450,000
Contract cost: 2016 -180,000
2017 -195,000
Gross Profit: 75,000
Estimated Cost to Complete:
12/31/2016 $200,000
12/31/2017 0
1. Assuming BCC uses the percentage-of-completion method of revenue recognition, the gross profit recognized in 2016 would be (rounded to the nearest thousand):
2. Assuming BCC uses the percentage-of-completion method of recognition the gross profit recognized in 2017 would be (rounded to the nearest thousand):
3. Assuming BCC used the completed contract method to recognize revenue, what would gross profit have been in 2016 and 2017 (rounded to the nearest thousand)?
2016 2017
a. $36,000 $39,000
b. $30,000 $45,000
c. $70,000 $5,000
d. $ 0 $75,000
4. Assuming BCC used the cost recovery method to recognize revenue under IFRS, what would gross profit have been in 2016 and 2017 (rounded to the nearest thousand)?

User Jay Achar
by
8.4k points

1 Answer

6 votes

Answer:

Step-by-step explanation:

Bid price - $450,000

Contract cost 2016- $ 180,000

Contract cost in 2017 - $195,000

Gross profit = $75,000

Estimated cost to complete at 2016 - $200,000

Percentage completion in 2016 - 180000/380000* 100 =47 %

Revenue recognized in 2016 - 47% * 450,000 = 211,500

Gross profit = 211,500- 180,000 = 31,500

2017

Revenue recognized - 53% = $238,500

Cost $195,000

Gross profit $43,500

3)Completed contract method -

Income are recognized when contract is completed

2016 - No revenue generated / recorded

2017

Revenue - 450,000

Cost to date - 375,000

Gross profit - 75,000

4) When using the cost recovery method under IFRS , an equal amount of income and revenue is recognized in the early life time of the project

2016

Income - 180000

Cost- 180000

Gross profit - 0

2017

Income -450000

cost 375,000

Gross profit - $75,000

User Deming
by
8.6k points