Answer and Explanation:
1. The computation of the material price variance is shown below:
= Actual Quantity × (Standard Price - Actual Price)
= 1,000 × ($20 - $19)
= $1,000 favorable
2. The computation of the direct material efficiency variance is shown below:
= Standard Price × (Standard Quantity - Actual Quantity)
= $20 × (3,000 pounds × 0.30 pounds - 1,000)
= $20 × (900 - 1,000)
= $2,000 unfavorable
3.The computation of the labor price variance is shown below:
= Actual Hours × (Actual rate - standard rate)
= 625 × ($11.75 per hour - $12 per hour)
= 625 × $0.25 per hour
= $156.25 favorable
4. The computation of the labor efficiency variance is shown below:
= Standard Rate × (Actual hours - Standard hours)
= $12 per hour × (625 hours - 3,000 containers × 0.20 hours)
= $12 per hour × 25 hours
= $300 unfavorable
If the standard cost is more than actual one so it would be favorable variance e and if the actual cost is more than the standard one so it would be unfavorable variance