Answer:
cost of machining per ceiling fan= $18 per unit
Step-by-step explanation:
Activity-based costing is a form of absorption costing where overheads are charged to product using cost drivers. Under this method, overheads are first analyzed and categorized by the activities responsible for them and then charged to product based on the amount of benefits enjoyed using cost drivers.
For example, the machining overhead would charged to each ceiling fan using the machining overhead rate per machine hours.
Cost of machining per ceiling fan = Machining hours × overhead rate per machine hours
= 2.50 × $7.20= $18 per unit
cost of machining per ceiling fan= $18 per unit