Answer:
Cost of The Land = $86,000 + $9,400 - $1,940 + $1,440 + $5,100
= $100,000
Therefore, Cost of The Land is $100,000.
Step-by-step explanation:
cost of constructing the building = $86,000
cost of demolishing old warehouse = $9,400
cost of salvaged materials = $1,440
Additional expenditures:
Attorney's fee = $5,100
Architects's fee = $8,940
Driveways and parking lot fee = $15,200