______is the difference between the early start and the late start days for a given

activity in a network diagram/CPM schedule.

A backward pass

Float

Slack

Duration

User Grinneh
by
5.4k points

1 Answer

2 votes
Answer: A backward pass

Explanation: A backward pass in the area of project management refers to the calculation of late finish dates and late start dates for the portions of schedule activities that have not been completed.