Answer and Explanation:
The computation of given question is shown below:-
The difference between the actual accumulated manufacturing overhead and the applied overhead measured on the basis of actual activity carried out at standard cost is the overhead expense under or over applied.
When applied overheads, the overheads are considered underapplied less than the actual overhead.
When overheads are applied, the overheads are considered overapplied higher than the real overhead.
So, we need to compute the applied overhead to find out the under or over applied overhead.
Applied Manufacturing Overhead = Total Machine Hours actually recorded × Predetermined Overhead Rate
= 20,700 MHs × $25
= $517,500
As we can see that the applied overheads are greater than the actual incurred overhead, so, Overheads are overapplied.
Over-Applied Overhead Cost = Applied Overhead – Actual Overhead
= 517,500 – 507,500
= $10,000
2. The preparation of schedule of cost of goods manufactured for the year is shown below:-
Chang Company
Schedule of Cost of Goods Manufactured
Direct materials:
Raw material, beginning $21,000
Raw material, purchases
(excluding indirect material
($410,000 - $16,000) $394,000
Raw materials available
for use $415,000
Less: Raw materials, ending ($31,000)
Raw materials use
in production $799,000
Add: Direct labor cost $70,000
Add: Applied Manufacturing
Overhead
(20,700 MHs × $25) $517,500
Total manufacturing costs $1,386,500
Add: Work in process,
beginning $41,000
Less: Work in process, ending ($71,000)
Cost of goods manufactured $1,356,500