Answer:
Applied Manufacturing Overheads are $102,000
Overapplied Manufacturing overheads are $18,000
Step-by-step explanation:
Under or over applied manufacturing overhead can be determined by comparing the actual and applied manufacturing overheads.
Applied overheads can be calculated by multiplying pre-determined overhead rate and actual level of quantity. Predetermined overhead rate is calculated using estimated overhead and estimated activity on which overheads are applied.
In this question the predetermined overhead rate is 120% of direct labor cost.
Applied overhead = Direct labor cost x 120% = $85,000 x 120% = $102,000
Actual overheads incurred = $84,000
Overapplied Manufacturing overheads = $102,000 - $84,000 = $18,000