Answer:
Total Overhead Variance= $500 unfavorable
Step-by-step explanation:
The total overhead variance is the difference between actual overhead and the applied overhead.
Actual Overhead = Variable + Fixed= $9500 + $6050= $ 15,550
Budgeted Overhead for 30000 direct labor hours = $ 150,000
Applied Overhead for 3000 hours = 3000 *$5= $15000
Total Overhead Variance= Actual Overhead Less Applied Overhead
= $15,500- $ 15000= $500 unfavorable
As actual is greater than applied it is unfavorable.