a plumber laying 500 meters of drain pipe required 20 men of working for 10 days . What length in meters would be laid by 50 men in 5 days, if they all work at the same rate?

User Zimkies
by
6.1k points

1 Answer

3 votes

Answer:

500 meters =20men =10days

To get the factor 500/(20*10)= 5/2 meters/day

For 50 men and 5days we don't know the meters

So we go by 50*(5/2)*5 =625meters