Answer:
0.11 hour
Step-by-step explanation:
According to the scenario, computation of the given data are as follow:-
Process time represents value added time = 1.7 hours
Throughput Time = Move Time + Queue Time + Process Time + Inspection Time
= 3.3 hour + 9.9 hour + 1.7 hour + 0.9 hour = 15.8 hour
Manufacturing Cycle Efficiency (MCE) = Value Added Time ÷ Throughput Time
= 1.7 hour ÷ 15.8 hour
= 0.11 hour
According to the analysis, the MCE was closest to 0.11 hour.