MC Qu. 34 Niemiec Corporation keeps careful track... Niemiec Corporation keeps careful track of the time required to fill orders. The times recorded for a particular order appear below: Hour Move time 3.3 Wait time 19.7 Queue time 9.9 Process time 1.7 Inspection time 0.9 The manufacturing cycle efficiency (MCE) was closest to: (Round your intermediate calculation and final answer to 2 decimal places.) Multiple Choice 0.11 0.95 0.19 0.05

User Terkel
by
6.3k points

1 Answer

4 votes

Answer:

0.11 hour

Step-by-step explanation:

According to the scenario, computation of the given data are as follow:-

Process time represents value added time = 1.7 hours

Throughput Time = Move Time + Queue Time + Process Time + Inspection Time

= 3.3 hour + 9.9 hour + 1.7 hour + 0.9 hour = 15.8 hour

Manufacturing Cycle Efficiency (MCE) = Value Added Time ÷ Throughput Time

= 1.7 hour ÷ 15.8 hour

= 0.11 hour

According to the analysis, the MCE was closest to 0.11 hour.