Answer:
$2,850
Step-by-step explanation:
The computation of total amount of budgeted direct labor for April is shown below:-
Total amount of budgeted direct labor = Buckets produced × (Estimated labor hour ÷ Half an hour needed for producing one unit bucket) × Labor rate
= 380 × (30 ÷ 60) × $15
= 380 × 0.5 × $15
= $2,850
Therefore for computing the total amount of budgeted direct labor for April we simply applied the above formula.