Answer:
$3,860
Step-by-step explanation:
According to the scenario, computation of the given data are as follows:
Expected activity:
Jobs = 18
Meals = 148
Cost = $550 per month
Cost per job = $77
Cost per meal = $13
So, Catering supplies in planning budget can be calculated as:
Catering supplies in the planning budget = $550 + (18 × $77) + ($13 × 148)
= $3,860