101k views
2 votes
Metro Facilities, Inc., contracts to sell a parking lot to Nouveau Property Company. The contract provides that if Metro does not close the deal by September 15, it must pay Nouveau one-half of the contract price. This provision is not enforceable because it is​

1 Answer

5 votes

Answer:

A penalty clause is a correct answer to this question.

Explanation:

A penalty clause differs from a clause on liquidated damages by not being tied to an estimate of potential actual damages. A provision stipulating an excessive monetary fee against a principal debtor in an agreement.

Courts usually do not impose such a provision, but may impose liquidated liability provisions when they provide a reasonable estimate of real damages.So penalty clause is the right answer .

User Alex Bagnolini
by
6.4k points