Answer and Explanation:
a. The journal entries are shown below:
1. Work in Process $72,000 ($120,000 × 60%)
To Factory Overhead $72,000
(Being the application of factory overhead is recorded)
2. Finished Goods $301,200
To Work in Process $301,200
(Being the job completed is recorded)
b. The balance is
= $75,000 - $72,000
= $3,000 debit
c. Moreover, it is under applied as the actual one is greater than the standard one
d. Now the cost of unfinished goods is
= Opening balance + direct material + direct labor + overhead - cost of goods finished
= $53,200 + $147,000 + $120,000 + $72,000 - $301,200
= $91,000
We simply applied the above formula