80.5k views
1 vote
A company has budgeted fixed overhead of $1.00 per hour at expected capacity of 5,000 units which have a standard quantity of 2 hours per unit. The company actually produces 5,200 units. The volume variance is

2 Answers

3 votes

Answer: 400 favorable is correct

Step-by-step explanation:

User Hillary
by
8.6k points
1 vote

Answer:

$400 favorable

Step-by-step explanation:

The computation of the volume variance is shown below:

Fixed overhead Volume Variance = Actual Overheads - Budgeted Overheads

where,

Actual overhead is

= 5,200 units × 2 hours × $1

= $10,400

And, the budgeted overhead is

= 5,000 units × 2 hours × $1

= $10,000

So, the volume variance is

= $10,400 - $10,000

= $400 favorable

We simply deduct the budgeted cost from the actual cost so that the difference could be come

User Prettyfly
by
8.2k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.