Smart Manufacturing budgeted costs for 50,000 linear feet of block are: Fixed manufacturing costs $24,000 per month Variable manufacturing costs $16.00 per linear foot Smart installed 40,000 linear feet of block during March. How much is budgeted total manufacturing costs in March?

1 Answer

6 votes

Answer:

$664,000

Step-by-step explanation:

The computation of the budgeted total manufacturing cost is shown below:

Budgeted total manufacturing costs is

= Fixed cost + Variable cost

= $24,000 + ($16 × 40,000 linear feet of block)

= $24,000 + $640,000

= $664,000

We simply added the fixed cost and the variable cost so that the total budgeted manufacturing cost could come