127k views
3 votes
Technical Performance Measurement (TPM) provides:

A. an estimate of performance as of a given date

B. a way of determining which performance measures are the most reliable

C. an forecast of ultimate performance given the current rate of development

D. a way for managers to make systematic tradeoff decisions concerning the performance of subsystems and components

User GibsonFX
by
5.4k points

1 Answer

4 votes

Answer:

The answer is option C) The answer is option Technical Performance Measurement (TPM) provides: a forecast of ultimate performance given the current rate of development.

Step-by-step explanation:

Technical Performance Measurement (TPM) is a yardstick used by companies to evaluate its performance levels. It is a standard tools that portrays the current performance strength of a system with respect to how well objectives are being met.

This information provided by TPM can be used by mangers to forecast of ultimate performance given the current rate of development.

User Pmttavara
by
5.4k points