116k views
3 votes
The standard cost card for a product indicates that one unit of the product requires 8 kilograms of a raw material at $0.80 per kilogram. The production of the product in April was 870 units, but production had been budgeted for 850 units. During April, 8,200 kilograms of the raw material were purchased for $6,888. All raw materials purchased were used. The material quantity variance for April was:

User Sinwav
by
3.4k points

1 Answer

6 votes

Answer:

Direct material quantity variance= $992 unfavorable

Step-by-step explanation:

Giving the following information:

Standard quantiy= 8kg

Standard cost= $0.8 per kilogram

Production= 870 unit

8,200 kilograms of the raw material was purchased for $6,888.

To calculate the material quantity variance, we need to use the following formula:

Direct material quantity variance= (standard quantity - actual quantity)*standard price

Standard quantity= 870*8= 6,960kg

Direct material quantity variance= (6,960 - 8,200)*0.8

Direct material quantity variance= $992 unfavorable

User Graham Mendick
by
4.2k points