The standard labor hours = $2,340
Step-by-step explanation:
Standard (Budgeted) production volume = 1000 trivets
Standard direct labor hours = 2,600
This means that:
1000 Trivets = 2,600 hours
∴ 1 Trivet = 2,600 ÷ 1,000 = 2.6 hours
Therefore, standard hours for 1 Trivet = 2.6 hours
Actual production volume in May = 900 units
Since we know the standard labor hours for production of 1 Trivet, the standard hours allowed in May is calculated as follows:
1 Trivet = 2.6 hours
∴ 900 Trivets = 2.6 × 900 = 2,340 hours
∴