Jeff Heun, president of Bridgeport Always, agrees to construct a concrete cart path at Dakota Golf Club. Bridgeport Always enters into a contract with Dakota to construct the path for $215,000. In addition, as part of the contract, a performance bonus of $32,000 will be paid based on the timing of completion. The performance bonus will be paid fully if completed by the agreed-upon date. The performance bonus decreases by $8,000 per week for every week beyond the agreed-upon completion date. Jeff has been involved in a number of contracts that had performance bonuses as part of the agreement in the past. As a result, he is fairly confident that he will receive a good portion of the performance bonus. Jeff estimates, given the constraints of his schedule related to other jobs, that there is 50% probability that he will complete the project on time, a 30% probability that he will be 1 week late, and a 20% probability that he will be 2 weeks late.

(a) Determine the transaction price that Concrete Always should compute for this agreement.
(b) Assume that Jeff Heun has reviewed his work schedule and decided that it makes sense to complete this project on time. Assuming that he now believes that the probability for completing the project on time is 90% and otherwise it will be finished 1 week late, determine the transaction price.

User Baduker
by
5.0k points

1 Answer

4 votes

Answer:

Transaction price $241,400

Transaction price $245,720

Step-by-step explanation:

Outcome Probability Contract Revenue Transaction Price

Complete on time 50% $215,000 + $32,000 = $247,000 $123,500

Complete one week late 30% $215,000 + $24,000 = $239,000 $71,700

Complete two weeks late 20% $215,000 + $16,000 = $231,000 $46,200

Transaction price $241,400

2

Outcome Probability Contract Revenue Transaction Price

Complete on time 84% $215,000 + $32,000 = $247,000 $207,480

Complete one week late 16% $215,000 + $24,000 = $239,000 $38,240

Transaction price $245,720