Answer and Explanation:
The computation of schedule for production is shown below:-
The processing requirements for the demand forecast result in a need for
Machine A = 80 × 10 + 60 × 10 + 40 × 5 + 20 × 5
= 1,700 ≤ 2,400
Machine B = 80 × 15 + 60 × 10 + 40 × 10 + 20 × 10
= 2,300 ≤ 2,400
Machine C = 80 × 15 + 60 × 10 + 40 × 15 + 20 × 10
= 2,500 ≥ 2,400
Machine D = 80 × 5 + 60 × 10 + 40 × 10 + 20 × 10
= 1,600 ≤ 2,400
The contribution margin per bottleneck minute is
Harlan = (200 - 40 - 40) ÷ 15
= $8 per minute
Gaylen = (150 - 30 - 30) ÷ 10
= $9 per minute
Leah = (100 - 20 -20) ÷ 15
= $4 per minute
Matthew = (75 - 10 - 10) ÷ 5
= $11 per minute
Therefore the products will be manufactured in the order that is Matthew, Gaylen, Harlan and Leah. So, the product mix of Matthews is 20 by using machine 100 minutes of Machine C, for Gaylen is 60 by using 600 minutes of Machine C, For Harlans is 80 by using 1,200 minutes of Machine C and For Leahs is 33 by using up the left 500 minutes of machine C time.