Answer:
1. Materials Conversion Costs
Total equivalent units of production 17,200 15,800
2. Cost per Equivalent Unit $ 4.05 $ 2.6
Step-by-step explanation:
Cutting Department
Weighted-Average Method
1. Equivalent Units
Particulars Units % of Completion Equivalent Units
Materials Conversion Materials Conversion
Transferred Out 13,700 100 100 13,700 13,700
Ending Inventory 3500 100 60 3500 2100
Total Equivalent Units 17,200 15,800
The Ending Inventory units are 3500 which are not yet complete.
Materials Conversion Costs
Total equivalent units of production 17,200 15,800
2. Cost Per Equivalent Units
Materials Conversion
Cost Added 69,660 18,480 + 22,600
Total Costs 69,660 41,080
Equivalent Units 17,200 15,800
Cost per Equivalent Unit 69,660 / 17,200 41,080/ 15,800
$ 4.05 $ 2.6
Cost of Ending Work In Process $ 19635
Materials = 3500 * $ 4.05= $ 14175
Conversion = 2100 * $ 2.6= $ 5460
We multiply the equivalent number of units with the cost per unit to find the cost.
Cost Of Units Transferred Out = $ 91,105
Materials = 13,700 * $ 4.05= $ 55,485
Conversion = 13,700 * $ 2.6 = $ 35620
B. A Cost Reconciliation Report
Materials Conversion
Ending WIP $ 14175 $ 5460
Transferred Out $ 55,485 $ 35620
Total $ 69660 41080
These calculated costs reconcile with the costs given in the above data.
Materials Conversion
Cost Added 69,660 18,480 + 22,600
Total Costs 69,660 41,080
These costs reconcile with the given costs.