After the designs have been created and approved, what is the first practical step in preparing for their construction? What are the second and third steps typically?

1 Answer

2 votes

Answer:

The steps are;

  • First step: Team assignment step
  • Second step: Procurement step
  • Third step: Construction step

Step-by-step explanation:

After design approval, the first practical step includes the assigning of the team to manage the project including the project manager, contract administrator etc. It is at the pre-construction step that the site for he construction is prepared for the actual construction.

The second step after the design have been created and approved is the procurement of goods, material and labor for the construction

The third step after the design have been created and approved is the actual construction of the design which begins with a pre-construction meeting followed by mobilization and construction on site.