Mundes Corporation uses the weighted-average method in its process costing system. The beginning work in process inventory in its Painting Department consisted of 2,700 units that were 60% complete with respect to materials and 40% complete with respect to conversion costs. The cost of the beginning work in process inventory in the department was recorded as $9,500. During the period, 8,700 units were completed and transferred on to the next department. The costs per equivalent unit for the period were $4.70 for material and $5.70 for conversion costs. The cost of units transferred out during the month was:

1 Answer

4 votes

Answer:

The cost of units transferred out during the month was:$ 99980

Step-by-step explanation:

Mundes Corporation

Current Costs Added

Units Transferred Costs $ 90480

Materials =8700 * $ 4.7= $ 40890

Conversion= 8700* $5.70= $ 49590

Costs from Preceding Department (WIP beginning Inventory)= $ 9500

Total Costs= Costs Added + Costs from Preceding Department

= $ 90480+ $ 9500= $ 99980

The Costs of units transferred out is $ 99980

The current costs are added to the preceding costs to get the total costs of the units transferred out.