Answer:
$38,880
Step-by-step explanation:
The calculation of direct material to be purchased is shown below:-
Direct materials to be purchased = (Budgeted Production × Number of raw material per unit) + Ending inventory - Beginning inventory
Direct materials to be purchased = (870 × 44) + 4,500 - 3,900
= $38,280 + 4,500 - 3,900
= $38,880
So, for calculating the direct material to be purchased we simply applied the above formula.