Answer:
$20,790,000
Step-by-step explanation:
Since the estimated total costs to complete had not change, the Construction is Process can be estimated as follows:
Construction in Process = Estimated total completion cost - Total costs of completion to date = $38,500,000 - $17,710,000 = $20,790,000