A company began construction of a new warehouse on Jan 1, 2018. The building was finished and ready for use on Sept 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 313,000 September 1, 2018 $ 465,000 December 31, 2018 $ 465,000 March 31, 2019 $ 465,000 September 30, 2019 $ 313,000 The company had $5,500,000 in 15% bonds outstanding through both years. The capitalized interest in 2018 was: