Answer:
Cost of completed units = $158,240
Step-by-step explanation:
Cost of completed units = Cost per equivalent unit × no of units
Equivalent unit = Degree of completion × units of work
Equivalent units of material
( 9200× 100%) + (3000×100%) = 12,200 unit
Cost per equivalent unit of material = $97,600/12,200 units= $8
Equivalent units of labour and overhead
(9200× 100%) + (3000× 25%) = 750
Cost per equivalent unit of labour and overhead
=( 73,630+17910)/9950 =$9.2
Cost of completed units
= $(9.2+8)× 9,200 = 158,240
Cost of completed units = $158,240