Answer :
Information turnaround time = 16.50 minutes
Explanation :
As per the data given in the question,
Cycle time of whole line = 1.50 minutes/unit
which means 1 unit is made in 1.50 minutes. In the line of 12 stations 1st step is the most error prone.
Error made at step 1 means that unit must be processed by 11 other stations in order to be made and inspected at 12th station.
The information turnaround time = cycle time × number of stations after error is made
=1.50 × 11
= 16.50 minutes