91.6k views
0 votes
LBC Corporation makes and sells a product called Product WZ. Each unit of Product WZ requires 2.3 hours of direct labor at the rate of $19.00 per direct labor-hour. Management would like you to prepare a Direct Labor Budget for June. The budgeted direct labor cost per unit of Product WZ would be: Multiple Choice $19.00 $5.60 $20.10 $43.70

1 Answer

2 votes

Answer:

$43.70

Step-by-step explanation:

Data provided

Each Unit Require = 2.3 hours

Direct Labor Rate Per Hour = $19.00

The computation of budgeted direct labor cost per unit is shown below:-

Budgeted direct labor cost per unit = Each Unit Require × Direct Labor Rate Per Hour

= 2.3 hours × $19.00 rate per hour

= $43.70

Therefore for computing the budgeted direct labor cost per unit we simply multiply the each unit require with direct labor rate per hour

User IAmKale
by
8.3k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.