Answer:
Right option is C.
Step-by-step explanation:
The operation manager will put the inventory in front of the process C. So, the right option is C.
As we have given the outputs of these processes:
Process A = 25 units/hr
Process B = 30 units/hr
Process C = 20 units/hr Lowest output among all processes.
As, we can see that the process C has the lowest output of all which is 20 units per hour. It clearly means that operation manager will utilize the low output of process C and put the inventory infront of process C in order to increase the output of the overall process.