Answer:
$7,000 Unfavorable
Step-by-step explanation:
data provided
Material in units = 18,000
Price per unit = 2
Actual hours = 38,000
Selling price = $3.50
The computation of material efficiency variance is shown below:-
Materials efficiency variance = (Standard hours - Actual hours) × Selling price
= (18,000 × 2 - 38,000) × $3.50
= $7,000 Unfavorable
Therefore for computing the material efficiency variance we simply applied the above formula.