Answer:
$ 2,504,000
Step-by-step explanation:
Budgeted overhead= $2,375,000
FOH budget variance= $129,000
Actual amount of fixed overhead= $2,375,000+$129,000
=$ 2,504,000
Therefore the actual amount of fixed overhead will be $ 2,504,000