Answer:
Amount transfer to finished goods is $1617000
So option (a) is correct answer
Step-by-step explanation:
We have given expected values of cost.
Overhead cost = $336000
Direct material cost = $400000
Direct labor cost = $240000
And actual value of cost
Over head cost = $840000
Direct material cost = $825000
Direct labor cost = $330000
Overhead is equal to
Therefore amount transfer to finished goods = $825000+$330000+$462000 = $1617000
So option (a) is correct