Answer:
Instructions are below.
Step-by-step explanation:
Giving the following information:
The standard quantity of clay used for each planter is 24 pounds. The company uses a standard cost of $ 2.15 per pound of clay. Lily produced 3,000 planters in May. In that​ month, 75,000 pounds of clay were purchased and used at the total cost of $ 153,000.
To calculate the direct material price and quantity variance, we need to use the following formulas:
Direct material price variance= (standard price - actual price)*actual quantity
Actual price= 153,000/75,000= $2.04
Direct material price variance= (2.15 - 2.04)*75,000
Direct material price variance= $8,250 favorable
Direct material quantity variance= (standard quantity - actual quantity)*standard price
Standard quantity= 3,000*24= 72,000 pounds
Direct material quantity variance= (72,000 - 75,000)*2.15
Direct material quantity variance= $6,450 unfavorable