Answer:
January February
Budgeted Material Cost $65,450 $340,500
Step-by-step explanation:
Direct materials budget for January and February .
January February
Production 1,950 units 2,110 units
Production Material needs (pounds) 9,750 10,550
Add Budgeted Closing Materials 8,440 4,700
Total Materials needed 18,190 15,250
Less Budgeted Opening Materials (5,100) (8,440)
Budgeted Materials 13,090 6,810
Cost per material = $ 50 per pound
Budgeted Material Cost $65,450 $340,500