233k views
2 votes
On January 3rd, Stevens Manufacturing received an order for 25 toasters. Following is the timeline for processing the order: Days Order processed 0.25 Wait for production to begin 2.00 Raw materials moved to assembly 0.25 Assembly 3.50 Wait for packaging 0.50 Toasters packaged 0.25 Wait for shipping 2.00 Toasters loaded and shipped 0.50 Toasters in transit to customer 5.00 Calculate the delivery cycle time. 14.25 days 9.25 days 5 days 13.75 days

User Jeudyx
by
5.3k points

1 Answer

2 votes

Answer:

The delivery cycle time is 9.25 days

Step-by-step explanation:

In order to calculate the delivery cycle time we have to make the following calculation:

delivery cycle time= Order processed days+ Wait for production to begin days+ Raw materials moved to assembly days+ Assembly days+ Wait for packaging days+ Toasters packaged days+ Wait for shipping days + Toasters loaded and shipped days

delivery cycle time=0.25 +2 +0.25 +3.5 +0.5 +0.25 +2+ 0.5

Delivery cycle time=9.25 Days

The delivery cycle time is 9.25 days

User Kus
by
5.4k points